We will be replacing the existing water mains and renewing service pipes that lead up to the boundaries of properties on the following streets.
When will the work take place?
The work on New Road will start on Thursday 24 July, for a duration of six weeks, before further work is carried out on Beechwood Avenue, Maple Way and Orchard Road from Monday 25 August to Sunday 5 October.
Our team will be working between the hours of 7:30 and 17:30 on weekdays. Weekend and overnight work may be required to limit traffic disruption on occasion.
Will traffic be affected?
To complete the work as safely and efficiently as possible, New Road will be closed for the initial duration of the mains renewal process - a suitable diversion route will be in place via the A505. Beechwood Avenue will then be closed once the second phase of work starts - another suitable diversion route will be put in place.