Planning a new development? |
| |
 |
Network development team |
Planning a new development?
The Cambridge Water Network Development Team
is your one stop shop for the design, pricing and construction of new water
mains, services to individual properties, building water supplies and other
temporary supplies to your development.
Whether it's a small, single building or a whole new
complex including retail, domestic and commercial properties, Cambridge Water
can provide and support all your water requirements for your new building
development.
You may wish to consider laying the mains yourself.
The attached document entitled
Company Specific Addendum identifies the process and standards we would
expect in this situation. Please contact us to discuss.
10 simple steps
-
Contact our Network Development office for an application form or further
advice by:
-
For one-off developments we post you an information pack,
together with an application form on the same day as your enquiry. Multi-unit
developments
are dealt with on a scheme-by-scheme basis. You will need to provide site
layout drawings from which we can design and cost the infrastructure required.
-
Where appropriate, complete the application form and return it to us by post
(our contact details are shown above). You should also
supply all relevant plans and supporting information. It is important that you
do your best to give as much detail and comprehensive information as possible
on the application form. This enables us to understand your needs better and to
provide you with a cost-effective proposal that is right for you. Please
remember, we need detailed plumbing drawings to ensure compliance with the
appropriate Water Fittings Regulations. A form is available to help you with
this. We can send it by post or it can be
downloaded from our website. Without these drawings, your
application may be delayed. If you need help to complete the form or require
further advice on a multi-unit development, please telephone us on 01223
403120.
-
We will process your application and support you from design stage to on-site
construction. Our cost-effective water supply proposals are based on the
information you provided and includes a design plan, offer letter and service
estimates. Our proposals are normally forwarded within 20 working days from
receipt of all the necessary supporting information. If an easement
(application to make use of adjoining land as for a right of way) is required,
we will let you know at this stage and provide all the information to guide you
through this legal process.
-
Once you have decided which of our services and proposals you prefer, you need
to pay for the water mains installation by sending a cheque (MADE PAYABLE TO
CAMBRIDGE WATER PLC) to Network Development, Cambridge Water Company, PO Box
275, Cambridge, CB1 3XF. The cost of the individual service connections will be
invoiced separately upon their completion.
-
Our Network Development Team are pleased to advise and support you throughout
the site construction programme. We review your construction schedule and
arrange installation of the infrastructure whenever you are ready.
-
You should inform our team when you need services to individual properties as
soon as possible. Before any connections can be made, the section of water pipe
from the property to the highway boundary (the supply pipe) MUST HAVE BEEN
LAID.
-
We inspect the supply pipe to ensure water fittings compliance and arrange a
site visit by our Customer Service Inspectors. You should allow five working
days notice for the visit .
-
Following a satisfactory outcome of the underground inspection, the connections
will be programmed into our work schedule. You should allow 21 days for the
work to be carried out.
-
When the plumbing installation is complete, please inform our team who will
arrange for the second inspection and the supply to be made live.
PLEASE NOTE:
We make every effort to accommodate your programme. But, service connections to
properties from the existing water mains network, involve opening the public
highway and are subject to statutory regulation. The Highway Authority requires
28 days notice before work commences on site. Under certain circumstances, we
may even have to provide three months advance notice. We therefore strongly
advise you request connections well ahead of your programme.

| |
Network
Development Team |
| |
Mike Sloan
Network Development Manager |
Head of network development.
This team is dedicated to meeting the needs of developers. Services include
design and costing of new infrastructures, to installation and on-site
maintenance.
|
Mobile 07765
234754
Direct 01223 403053
E-mail mikesloan@
cambridge-water.co.uk |
| |
Craig Claydon
Network Development Technician
|
Responsible for design and
costing of the network infrastructures required to
service new developments.
|
Mobile 07900 270059
Direct 01223 403036
E-mail craigclaydon@
cambridge-water.co.uk |
| |
Matt Jackson
Water Regulation Officer |
Responsible for developer's compliance with the Water Fittings Regulations.
(WFRs). WFR apply to all plumbing systems new and old, from the underground
supply pipe to all around the building. They ensure our customers receive high
quality drinking water. Our team of Customer Service Inspectors carry out
hundreds of on-site tests each year to ensure compliance. |
Mobile 07900 270062
Direct 01223 403033
E-mail mattjackson@
cambridge-water.co.uk |
| |
Carol Jackson-Smith
Administrator
Jessica Groom
Administrator
|
Provide administration support
and help for customers with general enquiries, service connections and plant
location enquiries.
|
Direct 01223 403120
E-mail networkdevelopment@
cambridge-water.co.uk |
|
|

|